Boro’ Foundry cuts induction furnace cooling costs with Meltech control system
Boro’ Foundry has upgraded its induction furnace cooling process with Meltech, replacing a fixed post-production run time with demand-led PLC control. The change cuts daily runtime by 5.5 hours, saves an estimated £5,448 a year and is expected to pay back in about 2.45 years.
Why it matters: - Boro’ Foundry says the upgrade reduces electricity use on a high-energy industrial process. - The shorter run time also reduces wear on pumps, motors and fans. - The project supports the foundry’s sustainability goals without requiring a major equipment replacement.
What happened: - Boro’ Foundry partnered with induction furnace technology specialist Meltech to modernise cooling operations at its West Midlands site. - The foundry moved from a fixed six-hour cooling run-on after production to an intelligent, demand-led PLC control system. - The new setup uses real-time communication between a PLC system and a Pulsar IGBT inverter. - The control system adjusts cooling activity based on actual temperature needs.
The details: - Induction melting systems depend on circulating water-cooling pumps and external fans to protect equipment. - The old process kept cooling equipment running at full capacity even when demand was lower. - The upgraded system automatically shuts down once optimal cooling is reached. - Cooling pump and fan runtime has fallen from 6 hours to 30 minutes after production. - The change saves 5.5 hours of energy use on every operating day. - Boro’ Foundry estimates the project will save £5,448 a year. - The system is expected to reach full payback in about 2.45 years.
Between the lines: - The project shows how industrial energy savings can come from control upgrades rather than new plant. - For heavy manufacturers, trimming idle runtime can deliver both utility savings and lower maintenance costs. - Sam Edwards, sales director at Boro’ Foundry, said efficiency gains can come from making smarter use of existing systems rather than major capital investment.
What's next: - Boro’ Foundry says the modernisation fits its broader commitment to sustainable manufacturing and continuous operational improvement. - The company points to its engineering capabilities and sustainability initiatives in a full case study for more information.
Disclaimer: This article was produced by AGP Wire with the assistance of artificial intelligence based on original source content and has been refined to improve clarity, structure, and readability. This content is provided on an “as is” basis. While care has been taken in its preparation, it may contain inaccuracies or omissions, and readers should consult the original source and independently verify key information where appropriate. This content is for informational purposes only and does not constitute legal, financial, investment, or other professional advice.
Sign up for:
Energy Update
The daily local news briefing you can trust. Every day. Subscribe now.
Check Your Email!
We sent a one-time activation link to: .
Confirm it's you by clicking the email link.
If the email is not in your inbox, check spam or try again.
Welcome back!
is already signed up. Check your inbox for updates.